Lingbao II HVDC Back-to-Back Project

Description

Situated on the border between central China’s Henan and Shanxi, Lingbao II project expanded the original asynchronous interconnection by an additional 750 MW and thus increases the possibilities of power exchange between the two grids. For this extension, C-EPRI Electric Power Engineering Co., Ltd. provided converter valves and control system components. This is the first project in the world adopting 6-inch 4500A thyristors.

Main Data

Execution period Feb.2008-Dec.2009
Rated DC Voltage 166.7kV
Rated DC Current 4500A
Rated Capacity 750MW




About Us
C-EPRI in Brief
Businesses
Management Team
History
Products & Solutions
Classic HVDC
HVDC Flexible
DC Grid
Services
Turnkey Solution
Simulation
Manufacturing
Testing
Maintenance & Training
R & D
HVDC Research Center
Research Programs
Articles and Papers
Academic Activities
Honors and Awards
Patents
Press Release
Features
Press Release